2009 WI 53
|
Supreme Court of |
|
|
|
|
Case No.: |
2007AP476 & 2007AP751 |
|
Complete Title: |
|
|
|
PRN Associates LLC and PGN Associates LLC, Plaintiffs-Appellants-Petitioners, v. State of Defendant-Respondent. PRN Associates LLC and PGN Associates LLC, Plaintiffs-Appellants-Petitioners, v. State of Defendant-Respondent. |
|
|
|
|
|
REVIEW OF THE DECISIONS OF THE COURT OF APPEALS 2008 WI App 103 Reported at: 313 (Ct. App. 2008-Published) and Reported at: 312 (Ct. App. 2008-Unpublished) |
|
|
|
|
Opinion Filed: |
June 17, 2009 |
|
Submitted on Briefs: |
|
|
Oral Argument: |
March 5, 2009 |
|
|
|
|
Source of Appeal: |
|
|
|
Court: |
Circuit |
|
County: |
Ozaukee & Dane
|
|
Judge: |
Paul V. Malloy & Maryann Sumi |
|
|
|
Justices: |
|
|
|
Concurred: |
|
|
Dissented: |
|
|
Not Participating: |
|
|
|
|
Attorneys: |
|
For the plaintiffs-appellants-petitioners there were
briefs by Joseph R. Cincotta and the Law Offices of Joseph R. Cincotta,
For the defendant-respondent the cause was argued by Richard E. Braun, assistant attorney general, with whom on the brief was J.B. Van Hollen, attorney general.
2009 WI 53
notice
This opinion is subject to further editing and modification. The final version will appear in the bound volume of the official reports.
REVIEW of decisions of the Court of Appeals. Affirmed.
¶1 ANN WALSH BRADLEY, J. The petitioner, Prism,[1] seeks review of two decisions of the court of appeals: (1) affirming the dismissal of Prism's petition for judicial review of an agency decision; and (2) affirming the dismissal of Prism's amended complaint for declaratory judgment.[2] These consolidated cases arise out of a dispute over a state procurement. Prism submitted a bid, but the contract was ultimately awarded to another developer. The Wisconsin Department of Administration ("DOA") denied Prism's protest, concluding that Prism was not entitled to the contract.
¶2 Prism asserts that its petition for judicial review of the DOA's determination was erroneously dismissed as moot. Specifically, Prism contends that it is entitled to relief——either money damages or the award of a state contract. It argues that the circuit court erroneously determined that Prism was required to enjoin the DOA from awarding the contract to another bidder in order to preserve its remedies.
¶3 Prism also contends that its amended complaint for a declaratory judgment was erroneously dismissed because sovereign immunity is not a bar to the action. In addition, it argues that the type of relief it seeks can be maintained as a declaratory action and that the legislature has consented to suit under Wis. Stat. § 775.01 (2007-08).[3]
¶4 We conclude Prism's petition for judicial review of the DOA's decision was properly dismissed. Even assuming that all of Prism's allegations are true, there is no relief that Prism can receive at this point. Although Prism could have sought an injunction to protect its interest, it failed to do so. Therefore, we determine that resolution of Prism's protest cannot have any practical effect on this existing controversy and it is therefore moot.
¶5 We further conclude that Prism's amended complaint for declaratory judgment was properly dismissed. Wis. Stat. § 775.01 does not waive sovereign immunity in this case because Prism has not complied with the statutory conditions precedent for initiating an action. Even if it had, a claim for the damages Prism seeks cannot be maintained in an action under § 775.01. Accordingly, we affirm the decisions of the court of appeals.
I
¶6 These consolidated cases originated with a document Prism filed in
Ozaukee County entitled "Petition for Review Pursuant to Wis. Stats. § 227.52 and § 227.53 and/or for
Declaratory Judgment Pursuant to
¶7 In October 2002, the University of Wisconsin-Milwaukee ("UWM")
and the
¶8 Prism submitted a bid which was selected by the evaluation committee. The Vice Chancellor of UWM sent Prism a letter which stated in part:
I am pleased to inform you that, after careful review
and consideration of the final proposals, the University and the Evaluation
Team has selected Prism Development Company as the developer UWM would like to
pursue negotiations with regarding the
On September 5, 2003, a resolution was passed granting the System the authority to negotiate a contract with Prism. Because of a lease-back provision in Prism's proposal, the State Building Commission's approval was also required.
¶9 A developer who had submitted a losing bid protested the selection of Prism pursuant to Adm Ch. 10. The developer argued that the selection process had been faulty. At the Building Commission's February 18, 2004 meeting, the System withdrew its request for approval. Subsequently, the System sent a letter to Prism explaining that the request had been withdrawn because "it became apparent that there was no support by [the State Building Commission]. That body's approval was essential to moving forward." The letter invited Prism to participate in a second round of bidding.
¶10 In March 2004, a second request for proposals ("the second RFP") was issued by the DOA Division of State Facilities at the direction of the State Building Commission. Prism again submitted a bid. At the same time and pursuant to Wis. Admin. Code Adm § 10.15, Prism filed Notices of Intent to protest the decision to withdraw consideration of the first RFP.
¶11 Prism's protest was denied and it appealed to DOA Secretary Mark Marotta. He denied the appeal as untimely, stating in part:
You have also indicated that you believe s. Adm 10.15(1), Code, allows you to both protest and appeal the decision of the University not to proceed further with the procurement. Section Adm 10.15, Code, allows a protest to be filed within 10 days after the issuance of a solicitation or after issuance of the letter of intent to award a contract. The solicitation in this matter was issued in October, 2002. Thus, your opportunity to protest and appeal decisions relating to the issuance of the solicitation are passed. No letter of intent [for the second RFP] has been issued.
Prism did not seek judicial review of this decision.
¶12 Prism alleges that it was "lulled into a belief that a Letter of Intent pursuant to Adm § 10.08 would be forthcoming" to alert those who had submitted bids that a developer had been selected. It believed that this letter was necessary to trigger its right to protest the selection of another developer. As Prism awaited the issuance of a letter of intent, it simultaneously participated in the second RFP.
¶13 In response to a January 26, 2005 letter requesting information, the DOA informed Prism that another developer, WEAS, had been selected as the winning bidder. The DOA's letter explained that Adm Ch. 10 did not apply to the second RFP process because the State Building Commission, a legislative body, authorized the RFP. Therefore, it concluded Prism was not entitled to protest the award under Adm Ch. 10.
¶14 Prism viewed the DOA's assertion that Adm Ch. 10 did not apply as "incorrect and incredible." In February 2005, Prism filed a Notice of Intent to Protest and a Protest pursuant to Adm § 10.15. The protest made the following claims: (a) Adm Ch. 10 did not permit the initial award to Prism to be rescinded, and by rescinding the award the System acted ultra vires;[5] (b) the System's withdrawal of the award to Prism was arbitrary and therefore void; (c) the issuance of the second RFP was contrary to law, ultra vires, and void; (d) the State should award the contract to Prism because it submitted the best proposal; and (e) the disclosure of Prism's initial bid was a violation of Adm Ch. 10, rendering the selection process for the second RFP void.
¶15 The System denied Prism's protest on March 25, 2005. It determined that the protest did not fit within the requirements of Adm Ch. 10 and that Adm Ch. 10 does not prohibit a procuring agency from abandoning a RFP prior to the issuance of a contract. It further determined that the second RFP, issued by the Building Commission, was not covered under Adm Ch. 10 and therefore could not be protested.[6] Prism appealed to the Secretary of the DOA pursuant to Adm § 10.15(5).
¶16 On June 6, 2005, DOA Secretary Mark Marotta issued a seven-page decision denying Prism's appeal. This decision is the subject of Prism's petition for judicial review, and it was attached to the petition.
¶17 Secretary Marotta's decision concluded that the System had the authority to withdraw its letter of intent to award Prism the project during the February Building Commission meeting. It further determined that because Prism did not appeal this decision on time, it had waived its right to object to the first RFP process. Additionally, it concluded that the second RFP was not governed by Adm Ch. 10 because it was issued by the Building Commission, which is a legislative rather than an executive commission.
¶18 Meanwhile, on March 15, 2005, the State and WEAS signed the
contract. At no point did Prism seek an
injunction in circuit court alleging that the DOA was acting beyond its
authority. The parties acknowledge that
the contract was subsequently executed by WEAS and the redeveloped
¶19 On July 6, 2005, Prism filed a "Petition for Review Pursuant
to Wis. Stats. § 227.52
and § 227.53
and/or for Declaratory Judgment Pursuant to
¶20 The Ozaukee County circuit court severed Prism's petition into two
independent actions——one
for judicial review of the DOA's administrative decision under Wis. Stat. Ch. 227, and one for
declaratory judgment. The
¶21 In Ozaukee County, the DOA filed a motion to dismiss for failure to state a claim. It asserted that even if all of the allegations contained in the petition for judicial review of the agency's decision were true, the case was moot because there was no relief that could be granted.
¶22 After a hearing on the merits, the circuit court granted the DOA's motion to dismiss.[8] The court stated, "in a Chapter 227 proceeding the question has to become what practical effect would a favorable decision to the plaintiffs have." It concluded that injunctive relief was not available——the contract had already been let to another bidder and performed. It further concluded that a wronged bidder was not entitled to a monetary (damages) remedy from the State under the relevant statutes, administrative code provisions, and the common law. Therefore, even if everything that Prism alleged was correct, the court concluded that there was no relief that could be granted and the claim was moot. Prism's motion to reconsider this decision was denied.[9]
¶23 In Dane County, the DOA also filed a motion to dismiss Prism's amended complaint for declaratory judgment for failure to state a claim. Among other arguments, it asserted that Prism's amended complaint should be dismissed for lack of personal jurisdiction because of sovereign immunity. The DOA argued that Wis. Stat. § 775.01, which permits some claims to be brought against the State, did not constitute consent to this suit. The circuit court concluded, "the state's motion to dismiss for lack of personal jurisdiction based on its immunity from suit must be granted because the state has not consented to this declaratory judgment action."[10]
II
¶24 These consolidated cases require us to address whether Prism's petition for judicial review was properly dismissed as moot. We are also required to address whether Prism's amended complaint for declaratory judgment was properly dismissed for failure to state a claim upon which relief can be granted.
¶25 An issue is moot when its resolution will have no practical effect
on the underlying controversy. State
ex rel. Riesch v. Schwartz, 2005 WI 11, ¶11, 278
¶26 Whether a complaint states a claim upon which relief can be
granted is also a question of law. Meyers
v. Bayer AG, 2007 WI 99, ¶21, 303
¶27 We accept as true both the facts in the complaint and the
reasonable inferences that may be drawn from such facts.
III
Ozaukee
¶28 We turn now to the question of whether the circuit court properly
dismissed as moot Prism's petition for judicial review. "The
general rule is that the court will not determine abstract principles of
law." City of
¶29 An
issue is moot when the court concludes that its resolution cannot have any
practical effect on the existing controversy.
Riesch, 278
¶30 The State argues that even if Prism is correct on the merits of its protest, a court resolution would have no effect on the existing controversy because there is no remedy that can be granted to Prism at this point. It contends that the petition for judicial review is therefore rendered moot. Thus, the question we must answer is: even if Prism's protest was improperly denied, is there any relief that it can receive now, almost three years after the project has been completed?
¶31 To determine whether the resolution sought can have any practical
effect on the existing controversy, we do not address the factual and legal
issues implicated in Prism's petition for judicial review. For purposes of this review, we assume that
Prism would be able to prove every fact and support every legal allegation in
its protest and petition for judicial review.
Rather, we examine Prism's requested relief. In its petition for judicial review, Prism
requested two distinct remedies: money damages for "the value of its
winning proposal" in the first RFP or award of the contract. We address each potential remedy in turn.
A
¶32 Prism asserts that it is entitled to money damages because it should have been awarded the contract under Adm Ch. 10, and the agency acted improperly when it instead let the contract to WEAS. Prism asserts that Adm § 10.15(2), which gives the DOA the authority to "settle and resolve" a protest, envisions a damages remedy for wronged bidders.[12] Yet, a money damages remedy would be contrary to the explicit purposes of Adm Ch. 10.
¶33 Adm Ch. 10 provides rules governing the State's procurement of contractual services. The purposes of the rules are, in part, "[t]o ensure that contracts for contractual services are entered into only in the best interests of the state," and "[t]o ensure that the state will procure at the lowest possible price, without sacrifice in quality, the contractual services required[.]" Adm § 10.02. Further, Wis. Stat. § 16.75 provides that with certain limited exceptions, contracts should be awarded to the "lowest responsible bidder."
¶34 It is an established proposition that procuring statutes and
regulations such as Adm Ch. 10 "are designed to prevent fraud, collusion,
favoritism and improvidence in the administration of public business, as well
as to ensure that the public receives the best work . . . at the most reasonable
price practicable." Aqua-Tech,
Inc. v.
¶35 Even though protection for an aggrieved bidder is not within the
purposes of a procurement regulation, a bidder has standing to contest an
agency's decision to award the contract to another developer. This is because a bidder "is in a
particularly good position to challenge the bidding authority's action and
thereby protect the rights of the public."
¶36 A damages remedy, however, thwarts the purpose underlying the
procurement statutes because it would require the taxpayers to pay twice for
just one completed project. The court of
appeals addressed a similar situation in D.M.K., Inc. v. Town of Pittsfield,
2006 WI App 40, 290 Wis. 2d 474, 711 N.W.2d 672. In that case, D.M.K. was the lowest bidder
on four municipal projects.
¶37 D.M.K. sued the town for lost profits.
If D.M.K. were successful in [recovering its purported
damages], the Town and its taxpayers would pay D.M.K.'s $216,000 in lost
profits in addition to the contract price paid to the contractor who
performed the work. On its face, this
result fails to benefit or protect the public.
¶38 Prism argues that because Aqua-Tech and D.M.K. both involved lawsuits against municipalities, they have no application to lawsuits against the State. This argument is unavailing. Like the statutes discussed in Aqua-Tech and D.M.K., the stated purpose of Adm Ch. 10 is to protect the taxpayer from unnecessary expenditures. Taxpayers are not protected when any governmental body pays twice for the performance of one contract——regardless of whether that governmental body is a municipality or the State. We conclude that the reasoning in Aqua-Tech and D.M.K. applies to this case and that Prism is not entitled to a damages remedy.
B
¶39 Prism also seeks as a remedy the award of the contract. It contends that as the winning bidder of the
first RFP process, it is entitled to the contract.[13] By the time Prism filed its petition for
judicial review of the agency decision,
however, the contract had already been signed.[14] In State ex rel. Hron Bros. Co. v. City of
Port Washington, 265 Wis. 507, 509, 62 N.W.2d 1 (1953), we stated, "[T]he fact that the
contract has actually been awarded to another is sufficient to induce the
courts to decline to interfere to further complicate the matter, even though
they might otherwise have done so." (quoting State ex rel. Phelan v.
Bd. of Educ., 24
¶40 Moreover, as the parties acknowledge, the Kenilworth redevelopment
project is finished and the
¶41 Because Prism cannot receive either money damages or an award of the contract at this point, there is no remedy that Prism can receive even if all of its factual and legal allegations are true. This does not mean, however, that Prism was always without a remedy.
¶42 It is undisputed that the DOA informed Prism that it was going ahead with contract negotiations with WEAS and that it did not intend to stay the negotiations to permit for resolution of Prism's protest.[15] Nearly six weeks elapsed between the date Prism was put on notice that there would be no automatic stay and the date that the contract with WEAS was signed. Yet Prism did not seek an injunction to prevent the contract from being awarded to WEAS.[16]
¶43 It is expected that an aggrieved bidder will "zealously
protect" the public interest and the public purse by taking legal action
to ensure that a contract is not awarded to the wrong bidder. See Aqua-Tech, 71
¶44 Prism asserts that an injunction would not have been available because sovereign immunity precludes a lawsuit against the State unless the legislature consents to the suit.[17] Here, there is no statute giving legislative consent for a suit to enjoin the State from awarding a contract to another bidder.
¶45 However, there is a "general exception to the rule of state
immunity" that would have been applicable here.
A general exception to the rule of state immunity for agencies or arms of the state, however, is that courts may entertain suits to enjoin state officers and state agencies from acting beyond their constitutional or jurisdictional authority. These suits are permitted because they are suits against individuals acting in excess of their authority.
¶46 In Prism's protest, filed before the contract was signed with WEAS, Prism contended that the System and the DOA were acting "ultra vires" because they did not follow the provisions of Adm Ch. 10 when they: (1) rescinded the initial award of the contract to Prism; (2) issued a second proposal; and (3) disclosed information from Prism's first bid. That is, Prism asserted that the DOA was acting without authority, which would have allowed Prism to seek an injunction against the agency. See id. Yet it did not do so.
¶47 It appears that Prism was aware of the necessity of seeking an injunction to preserve its interest in the contract. Instead of filing for an injunction, however, Prism sought assurances from attorneys for the DOA that it need not seek an injunction and would be permitted to seek a damages remedy.[18] Based on the correspondence provided by Prism, these assurances were not given. Ultimately, Prism attained neither an assurance that a damage remedy was available nor an injunction that could have preserved its interest in the contract.
¶48 It should have been apparent to Prism that under Wisconsin law, a
damages remedy likely was unavailable and that an injunction was required to
protect any interest it had in the
¶49 We conclude that the
IV
¶50 We turn next to the action for declaratory judgment under Wis. Stat. § 804.06, which was dismissed on the grounds of sovereign immunity. Prism filed an amended complaint in Dane County seeking the following relief: (1) a declaration that the DOA should have awarded the contract to Prism and violated Adm Ch. 10 by not doing so; (2) a declaration that the DOA prevented and denied Prism the opportunity to protest under Adm Ch. 10; (3) a declaration that as the winning bidder of the first RFP, Prism had either a contract or an exclusive right to negotiate for a contract; (4) a declaration that the DOA violated Adm Ch. 10 by releasing the contents of Prism's first proposal to the public; and (5) a declaration that the DOA acted ultra vires by authorizing and conducting the second RFP.
¶51 As discussed above, the State cannot be sued without its consent,
and the legislature directs the manner in which suits may be brought against
the State. See
¶52 Like other lawsuits, actions for declaratory relief can be
dismissed on the grounds of sovereign immunity.
Nonetheless, there are occasions when a suit for declaratory judgment
against a state agency is permissible. In Lister, we explained:
[T]he court has [] recognized that the declaratory judgment procedure is particularly well-suited (in cases where such relief is otherwise appropriate) for resolving controversies as to the constitutionality or proper construction and application of statutory provisions. As a result, it has been necessary to engage in a fiction that allows such actions to be brought against the officer or agency charged with administering the statute[.]
¶53 Declaratory judgment provides prospective rather than remedial relief. The purpose of declaratory relief and Wis. Stat. § 806.04, the Uniform Declaratory Judgments Act, is:
to enable controversies of a justiciable nature to be brought before the courts for settlement and determination prior to the time that a wrong has been threatened or committed. The purpose is facilitated by authorizing a court to take jurisdiction at a point earlier in time than it would do under ordinary remedial rules and procedures.
¶54 In Lister, a group of students brought suit against the
University of Wisconsin Board of Regents.
The students argued that they had been classified as non-residents
contrary to the Wisconsin Statutes and therefore had to pay tuition at a higher
rate. Among other remedies, they sought
a declaratory judgment of their right to have been classified as
residents.
¶55 This court concluded that the action for a declaratory judgment could not be maintained. We said:
A court cannot close its eyes to the purpose which a
declaration of rights will serve in the particular case. It is not a sufficient ground for declaratory
relief that the parties have a difference of opinion as to the proper
construction and application of a particular statute. No anticipatory or preventative relief is
sought in this action. To the extent
that the complaint attempts to state a claim to relief under state law, the
only consequence which the desired declaration of rights could have would be to
settle the plaintiffs' rights to recover the amounts paid in nonresident
tuition. The action is, in effect,
one for damages.
¶56 The situation here is analogous to the situation in Lister. The declarations Prism seeks all relate to the DOA's past actions, such as failing to award the contract to Prism, rescinding the first RFP, and issuing a second RFP. None relates to the State's future conduct. In effect, Prism seeks a declaration that its rights were violated during the procurement procedure so it can pursue a damage remedy against the State.[20]
¶57 "A declaration which seeks to fix the state's responsibility
to respond to a monetary claim is not authorized by
¶58 Nonetheless, Prism argues that its amended complaint is justiciable because Wis. Stat. § 775.01 waives sovereign immunity and authorizes suit against the State for contract actions that would render the state a debtor. Wis. Stat. § 775.01 provides:
Upon the refusal of the legislature to allow a claim
against the state the claimant may commence an action against the state by
service . . . and by filing with the
clerk of court a bond . . . to the effect that the
claimant will indemnify the state against all costs that may accrue in such
action . . . in case the claimant fails to
obtain judgment against the state.
Chapter 775 is limited to
claims which, "if valid, would render the State a debtor to the
claimant." Brown, 230
¶59 Prism's argument that Section 775.01 authorizes this lawsuit is
unpersuasive for two reasons. First,
Prism is procedurally barred from relying on Wis. Stat. Ch. 775 because it has not met the conditions
precedent for filing such a claim.
Before a Chapter 775 claim can be filed, the following conditions must
be met: (1) the claim must be submitted to the legislature; (2) the claim must
be denied; and (3) the claimant must file a bond with the clerk of courts.
¶60 Prism acknowledges that it has not satisfied these statutory requirements. Rather, it contends that the Claims Board declined to take any action on the claim until the court case was completed because the Claims Board is a forum of last resort. Prism argues that it was placed in a Catch-22 situation because it could not file a claim until this court case was complete, but it could not be granted relief in court unless it could demonstrate that the legislature authorized suit.
¶61 This argument is not persuasive. Here, Prism filed an action in court seeking a declaration of rights, presumably so that it could later file a claim for money damages with the legislature. In order to have personal jurisdiction over the DOA, however, we must first conclude that the legislature authorized this suit. The legislature has not authorized this suit against the State unless Prism has followed the conditions precedent for bringing suit. It has not done so here.
¶62 Second, the damages Prism seeks are not the type that are
authorized under Section 775.01 as that statute has been interpreted by the
courts. In Koshick v. State, 2005
WI App 232, 287
¶63 The court of appeals interpreted a long line of cases to determine
whether Koshick could maintain a breach of contract claim under § 775.01 for lost
profits and expenses incurred. Relying
on a 1952 case, Trempealeau County v. State, 260
¶64 The facts in this case are similar to the facts in Koshick. As in Koshick, Prism claims that it had a contract with the State and it seeks damages for the cost of preparing its winning bid and for "the value of the contract."[22]
¶65 Prism does not assert that its ch. 775 action can be maintained under the holding of Koshick. Instead, it contends that Koshick was wrongly decided. In essence, Prism concedes that we must overrule Koshick to permit Prism's claim under Section 775.01 to go forward.
¶66 We decline to do so here. It is the role of the legislature, rather than that of the court, to consent to suit against the State. The Koshick court relied on the text of the statute and existing case law when it concluded that a breach of contract action for lost profits and expenses incurred could not be maintained under § 775.01.[23]
¶67 We conclude that Prism cannot maintain a declaratory action against the DOA because Prism is seeking money damages rather than anticipatory or preventative relief. We further determine that Wis. Stat. § 775.01 does not waive sovereign immunity in this case because Prism has not complied with the statutory conditions precedent of that section and because even if it had, the damages Prism seeks cannot be maintained in an action under § 775.01.
V
¶68 In sum, we conclude Prism's petition for judicial review of the DOA's decision was properly dismissed. Even assuming that all of Prism's allegations are true, there is no relief that Prism can receive at this point. Although Prism could have sought an injunction to protect its interest, it failed to do so. Therefore, we determine that resolution of Prism's protest cannot have any practical effect on this existing controversy and is therefore moot.
¶69 We further conclude that Prism's amended complaint for declaratory judgment was properly dismissed. Wis. Stat. § 775.01 does not waive sovereign immunity in this case because Prism has not complied with the statutory conditions precedent for initiating an action. Even if it had, a claim for the damages Prism seeks cannot be maintained in an action under § 775.01. Accordingly, we affirm the decisions of the court of appeals.
By the Court.—The decisions of the court of appeals are affirmed.
[1] Plaintiffs PRN Associates LLC and PGN Associates LLC are collectively referred to as "Prism" throughout this opinion.
[2] See PRN Associates v. Wis. Dep't Admin., 2008 WI App 103, 313 Wis. 2d 263, 756 N.W.2d 580, affirming orders of the circuit court for Ozaukee County, Paul V. Malloy, Judge; PRN Associates v. Wis. Dep't Admin., No. 2007AP751, unpublished slip op. (Ct. App. May 15, 2008), affirming a judgment of the circuit court for Dane County, Maryann Sumi, Judge.
[3] All subsequent references to the Wisconsin Statutes are to the 2007-08 version unless otherwise indicated.
[4] Wis. Stat. § 16.705(2) authorizes
the DOA to promulgate rules regulating "the procurement of contractual
services." These rules are
contained in Wis. Admin. Code Adm
In relevant part, Adm § 10.15 states:
(1) Right to protest. Any bidder or proposer . . . who is aggrieved in connection with a solicitation or a notice of intent to award a contract may protest to the procuring agency. . . .
(2) Authority to resolve protests. The head of the procuring agency, or designee, shall have the authority to settle and resolve a protest of an aggrieved bidder or proposer concerning the solicitation or intent to award a contract.
. . .
(5) Appeal. The protester may appeal a decision of the procuring agency . . . to the secretary . . . .
(6) State of procurements during protests. In the event of the filing of a timely notice of intent to protest, protest, or appeal . . . the state shall not proceed further with the solicitation or with the award of the contract until a decision is rendered in response to the protest or appeal, or unless the secretary, after consultation with the head of the contracting agency, makes a written determination that the award of the contract without delay is necessary to protect substantial interests of the state.
[5] "Ultra vires" is defined as: "Unauthorized; beyond the scope of power allowed or granted by a corporate charter or by law." Black's Law Dictionary 1525 (7th ed. 1999).
[6] The DOA continued to advance the position that Adm Ch. 10 was inapplicable to the circuit court, the court of appeals, and in its brief to this court. Prism argues that even if Adm Ch. 10 was an inappropriate procedure to use, the State initiated the second RFP under Adm Ch. 10 and was bound to follow the Adm Ch. 10 procedures when Prism filed its protest.
At oral argument, counsel for the DOA acknowledged: "Judge, I couldn't make a cogent argument that [the State did not initiate the second RFP under Adm Ch. 10]. Does it apply in these types of cases? No. I think it applies here [however] because that's the way [the DOA initially] treated it."
[7] Prism sought the following relief in paragraph 24 of its petition:
a. a
determination that the State was estopped from arguing that "Prism is
precluded, for any reason, from challenging . . . [the actions of UWM and
the System] to withdraw and/or rescind the award of the
b. a determination that the procedures used in both RFPs were irregular and not in compliance with law;
c. a determination that the DOA's conclusion that the matter is not governed by Adm Ch. 10 was erroneous;
d. a determination that it was improper to rescind the initial selection of Prism because Adm § 10.08 provides that the contract shall be awarded to the bidder selected by the evaluation committee;
e. a determination that the actions of the System and the DOA were ultra vires;
f. a determination that Prism is entitled to a remedy——either the award of the contract or economic damages.
[8] The circuit court granted the DOA's motion to dismiss for failure to state a claim upon which relief can be granted. It is unclear whether dismissal for failure to state a claim is an appropriate procedure for dismissing a petition for judicial review of an agency decision.
In
Nevertheless, a petition for review of an agency decision can be dismissed if it is moot:
A motion to dismiss for mootness . . . does not request a determination on the merits. When a case is dismissed because the issues therein have become moot, the rights of the parties are not adjudicated, and neither party is entitled to judgment. All that is involved . . . is a conclusion by the court that the determination sought cannot have any practical effect upon an existing controversy.
We proceed to examine the circuit court's determination that Prism's protest is moot because it is the essence of the circuit court's decision.
[9] Under Wis. Stat. § 227.55, the agency under review must transmit the record to the reviewing court. Yet, in this case the agency's record was never transmitted to the circuit court and is therefore not part of the record on appeal. Normally, the absence of the agency's record would foreclose our ability to review the agency's decision. Here, however, the basis for the circuit court's dismissal of the case, mootness, is a legal determination that does not address the merits of the agency's decision. The circuit court commented, "The record should be here. But, legally, the matter would be moot, whether or not the record is filed."
[10] After oral argument in this court, Prism filed a motion to supplement the record with the Department of Justice's investigation into Secretary Marotta and the Kenilworth Building Project. We granted Prism's motion over the objection of the DOA. The investigation concluded that "[t]here is no evidence, either from the investigation and interviews or from the case documents, to substantiate Prism's allegations against Marotta." We do not further discuss the facts contained in the investigation because they do not illuminate our task of determining whether Prism's petition for judicial review and amended complaint were properly dismissed.
[11] A court will make an exception
and consider a moot issue under certain circumstances. For instance, a court may decide a moot issue
if it is of great public importance or arises frequently enough to warrant a
definitive decision to guide the circuit courts. State ex rel. Riesch v. Schwartz, 2005
WI 11, ¶12, 278
[12] Adm § 10.15(2) provides: "The head of the procuring agency, or designee, shall have the authority to settle and resolve a protest of an aggrieved bidder or proposer concerning the solicitation or intent to award a contract."
[13] As authority for this proposition, Prism cites Adm § 10.08(7), which states: "Award shall be based on the evaluation committee recommendation . . . ."
[14] The contract was signed on
March 15, 2005, and Prism filed its petition for review with the circuit court
in
[15] Adm § 10.15(6) provides that the DOA will impose a stay in a procurement proceeding while a protest is pending:
In the event of the filing of a timely notice of intent to protest, protest or appeal . . . , the state shall not proceed further with the solicitation or with the award of the contract until a decision is rendered in response to the protest or appeal, or unless the secretary . . . makes a written determination that the award of the contract without delay is necessary to protect substantial interests of the state.
[16] Prism asserts that
under Adm
[17] See
[18] This allegation does
not appear in either the petition for judicial review or the amended
complaint. Prism attempted to submit
correspondence in support of this argument in the
[19] Prism requests that we send the case back to the DOA to ask the Secretary to "settle and resolve" its protest under Adm § 10.15(2). We fail to see how this action would accomplish anything other than to further extend this already protracted dispute. The DOA cannot award the contract to Prism when it has been let to another bidder and fully performed. Further, awarding Prism money damages would be contrary to the purposes of the procurement regulations as discussed above.
Under these circumstances, sending the case back for the DOA to "settle and resolve" a protest that it has already denied would amount to an exercise in futility.
[20] In its brief, Prism stated:
"The ultimate objective is a money judgment against the State," and
that "The declaratory judgment is prefatory to further action for actual
relief."
At oral argument, Prism's attorney clarified that it sought a declaratory judgment so it could ultimately receive money damages: "[Damages] are contemplated strongly in [Adm Ch. 10]. There is really no other meaningful relief that can be granted. . . . What I would cite to is 775 certainly contemplates money being paid to contracting parties who lose out and their contract is breached." Counsel later continued: "What I need the court to say is Adm 10 applies; Adm 10.08 says the contract shall be awarded to the winner[.] . . . and [the court] should I think——I hope it does——address the issue of the type of relief available in the Adm 10.15 protest and appeal proceedings."
[21] See Trempealeau County v. State, 260 Wis. 602, 51 N.W.2d 499 (1952) (permitting the county to bring an action under the predecessor to the current § 775.01 to recover money mistakenly paid to the State for hunting and fishing licenses issued by the county); Boldt v. State, 101 Wis. 2d 566, 568, 305 N.W.2d 133 (1981) (permitting a claim for recovery of certain Social Security payments the State had received on the plaintiff's behalf).
[22] At oral argument, one of the justices commented, "What you're asking for here as I understand it is the money damages for the cost of putting together a proposal." Prism's counsel responded, "We want at least that. We also want the value of that proposal. Which is——I mean, don't say lost profits, but I think there is some value to that proposal that is substantial."
[23] Prism also argues that
the takings clause of the Wisconsin Constitution is an exception to sovereign
immunity that applies in this case. See