|
COURT OF APPEALS DECISION DATED AND FILED September 16, 2008
David R. Schanker Clerk of Court of Appeals |
|
NOTICE |
|
|
|
This opinion is subject to further editing. If published, the official version will appear in the bound volume of the Official Reports. A party may file with the Supreme Court a petition to review an adverse decision by the Court of Appeals. See Wis. Stat. § 808.10 and Rule 809.62. |
|
APPEAL
from a judgment of the circuit court for
Before
¶1 PER CURIAM. Peter Johnson and Karen Johnson Peters (collectively, Johnson) appeal a summary judgment granted in favor of Enbridge Energy. Johnson argues that Enbridge’s use of land outside an easement and construction of additional pipelines within the easement constitute a taking that calls for the commencement of condemnation proceedings. Alternatively, Johnson challenges the easement as unenforceable and against public policy. We reject Johnson’s arguments and affirm the judgment.
Background
¶2 Johnson owns two parcels of real property in
¶3 In 2006, Enbridge notified Johnson that it would be exercising its easement rights to construct a third and fourth pipeline parallel to the existing pipelines. Consistent with its interpretation of rights granted under the easement, Enbridge determined it needed to use a 100-foot strip of land immediately adjacent to the right-of-way during construction of the pipelines. When Johnson balked at Enbridge’s use of the adjacent land, Enbridge obtained a temporary restraining order and filed the underlying declaratory judgment action. Johnson counterclaimed for inverse condemnation and trespass, asserting the easement is unenforceable. Following a hearing, the circuit court enjoined Johnson from interfering with construction of the pipelines. After additional discovery, the parties moved for summary judgment. The court granted summary judgment in favor of Enbridge and this appeal follows.
Discussion
¶4 This court reviews summary judgments independently, applying
the same standards as the circuit court.
Smith v. Dodgeville Mut. Ins. Co., 212
¶5 Johnson argues that Enbridge’s use of the 100-foot strip of land adjacent to the right-of-way constituted a “taking,” thus requiring the commencement of condemnation proceedings. Condemnation proceedings are appropriate when an entity with condemning authority is occupying property “without the right to do so.” See Wis. Stat. § 32.10. Here, the easement conveys, in relevant part:
A right-of-way and perpetual easement to construct, operate, maintain, inspect (including aerial patrol), remove, replace and reconstruct one or more pipelines together with valves, fitting, protective apparatus and all other equipment and appurtenances as may be convenient in connection therewith for the transportation of oil, other liquid hydrocarbons, and any product or by-product thereof, or any material or substances which can be conveyed through a pipeline on, over, under and across [the subject property], together with the right to clear and to keep cleared the Right-of-Way so as to prevent damage or interference with its efficient operation and patrol. The Grantor further grants the Grantee the right of ingress and egress to and from the Right-of-Way for all purposes convenient or incidental to the exercise by the Grantee of the rights herein granted, together with the right to use the lands immediately adjacent to each side of the Right-of-Way as is reasonably required during construction. (Emphasis added).
Because the easement grants Enbridge the right to use land immediately adjacent to the right-of-way, condemnation is not necessary.
¶6 Johnson nevertheless challenges the easement as unenforceable
and against public policy, claiming the ambiguity of the term “lands
immediately adjacent” affords Enbridge unlimited access to Johnson’s
property. On the contrary, the easement
limits Enbridge to the “use of lands immediately adjacent … as is
reasonably required during construction.”
If there were a disagreement between the parties over what amount of
land was “reasonably required during construction,” that dispute could have
been resolved by the circuit court. Here,
Johnson does not contest Enbridge’s claim that 100 feet was reasonably required
under the existing circumstances but, rather, challenges the general notion of
what may be “reasonably required”
under various hypotheticals not relevant to the present case. This court will not decide issues based on
hypothetical or future facts. Pension
Mgmt., Inc. v. Du Rose, 58
¶7 Next, Johnson asserts the parties could not have intended the use of “significant amounts” of land adjacent to the right-of-way because the easement contains “no method of compensation” for Enbridge’s use of those lands. The term “significant amounts,” however, is relative and, as noted above, any dispute over what is “reasonably required during construction” could be resolved by the court. In any event, with respect to compensation, the easement provides:
The Grantee shall … pay to the Grantor for the rights herein granted the sum of
$130.00 which when added to the sum paid herewith shall be equivalent to $33.00
per
Johnson cites the deposition testimony of Douglas Aller, Enbridge’s “supervisor of lands and right-of-way,” to support the proposition that the easement provides no method of compensation for the use of lands immediately adjacent to the right-of-way. Although Aller testified he did “not see an actual calculation for that in the easement,” Aller further testified that compensation for use of the adjacent lands was included in the $33 per acre payment required by the easement. In any event, under the plain language of the easement, compensation is provided “for the rights therein granted,” which includes the right to use lands immediately adjacent to the right-of-way.
¶8 Citing Lehner v. Kozlowski, 245
[W]here a grant of an easement is general as to the extent of the burden to be imposed on the servient tenement, an exercise of the rights, with the acquiescence and consent of both parties, in a particular course or manner, fixes the right and limits to the particular course or manner it had been enjoyed.
¶9 Here, the easement provides: “The aforesaid rights and easement are granted as and from the date hereof and for so long thereafter as the Grantee desires to exercise the same on the following terms and conditions which are hereby mutually covenanted and agreed to by and between the Grantor and the Grantee.” (Emphasis added.) The easement further provides: “Should the Grantee at any time construct more than one pipeline hereunder, it will pay the Grantor, prior to construction of each such additional pipeline, the same consideration as is payable under this clause for the initial pipeline.” (Emphasis added.)
¶10 To the extent Johnson challenges Enbridge’s right to construct additional pipelines within the right-of-way, the clear language of the easement establishes that the parties contemplated the construction of additional pipelines. Moreover, by failing to contest construction of the second pipeline in 1997, Johnson’s own conduct demonstrates he did not believe Enbridge’s rights under the easement were limited to the construction of only the initial pipeline. Johnson likewise asserts Enbridge’s use of adjacent land is restricted to the amount of land used when the initial pipeline was constructed. However, unlike the easement in Lehner, the present easement anticipates future construction and grants Enbridge the right to use lands immediately adjacent to the right-of-way as is reasonably required “during construction.” The easement, therefore, does not limit Enbridge’s use of adjacent lands to that used during initial construction.
¶11 Finally, Johnson argues the easement is impermissibly
exculpatory. Exculpatory contracts are
defined as “contracts which relieve a party from liability for harm caused by
his or her own negligence.” Merten
v. Nathan, 108
By the Court.—Judgment affirmed.
This opinion will not be published. See Wis. Stat. Rule 809.23(1)(b)5 (2005-06).